Hoega Kusten Bridge, Sweden

HMV designed, manufactured and supplied the Air Spinning Equipment for Scandinavian Bridge Joint Venture.
The wire was supplied in coils and transferred to 20 ton drums in a separate reeling shop on site. This was HMV’s first spinning project and based on well proven tramway competence the spinning of the 8000 tons of wore was carried out successfully.
The equipment combined modern tramway design with well proven Air Spinning method.
The spinning was completed in November 96 under rough winter conditions according to the Free Hanging method with Paul H. Mueller as the consultant for the spinning.
HMV also supplied the cable wrapping machines for this project